Graduation of Internal routing change to production environment.
Scheduled Maintenance Report for Tropo
Completed
The scheduled maintenance has been completed.
Posted 11 months ago. Mar 14, 2018 - 01:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 12 months ago. Mar 13, 2018 - 00:00 EDT
Scheduled
WHAT? :
* Internal routing change for how Gateways commuicate with Runtimes.

WHEN?:
* Tuesday 3/13/2018, scheduled from 9:00pm -et through 01:00am.

IMPACT:
* There will be no downtime; work will be conducted on redundant systems removed from availability. This change has been soaking in integration & developer platforms for the last week and there have been no issues.

WHY?
* Address signaling issues between gateway and runtime to ensure correct transport is used, especially when clients are not using UDP.
Posted 12 months ago. Mar 09, 2018 - 15:44 EST