Shared Production env upgrade
Scheduled Maintenance Report for Tropo
Completed
We have decided to postpone tonight's maintenance, and will follow up later this week with details of when the upgrade will be rescheduled.
Posted 14 days ago. Feb 06, 2018 - 18:21 EST
Scheduled
WHAT?
* Deploying the latest build (15.11.1) to the Shared Production environment.
* All Tropo.com usage currently runs in the SJC datacenter; at this time we will route all traffic (Shared & Dedicated) to the WDC datacenter.

WHEN?
* Tuesday 2/6/2018, scheduled from 9:00pm -et through 11:00pm.

IMPACT:
* There will be no downtime or reduced capacity. When traffic is flipped to WDC the updates will be live.

WHY?
* Latest and greatest with a few minor enhancements and corrections. Visit changes.tropo.com for more details.
* Switching datacenters so we can safely conduct some heavy-lifting maintenance in SJC.
Posted 18 days ago. Feb 02, 2018 - 17:49 EST